Update on March 14, 2018 |
Highland Gate Redevelopment
Park Construction Update June 2023
Highland Gate Central Park is now open!
Construction of the new Highland Gate subdivision is being done in phases. Phase 1 is close to completion of 44 units. Currently, Phases 2A, 2B, 3 and 4 subdivision agreements have been registered with construction underway.
Below is a colour map showing the Phasing Plan for the entire subdivision.
Vegetation Management Plans:
Vegetation Management Plan have been submitted to the Town for the following phases:
Update on October 20, 2017 |
Servicing and Road Construction for Phase 1 will be commencing by the week of October 23, 2017. |
Update on September 21, 2017 |
On September 21, 2017, Town of Aurora staff met with Highland Gate Developments Inc. ("HGDI"), Highland Gate Rate Payers Group ("HGRPG") and the Ad-Hoc Park Committee. This meeting was an opportunity for all attendees to provide comment on the detailed design which incorporated ideas and concepts from the initial meeting. Both the HGRPG and the Ad-Hoc Park Committee were pleased with the progress on the parkland drawings and detailed features.
|
Update on August 1, 2017 |
On July 24, 2017, Town of Aurora staff met with Highland Gate Developments Inc. ("HGDI"), Highland Gate Rate Payers Group ("HGRPG") and the Ad-Hoc Park Committee. The meeting was an opportunity for all parties to provide comment, share ideas and relay concerns. It was agreed that HGDI direct the landscape design consultant to start the detailed design stage of this project. This will allow all parties to continue to work together. This meeting was highly productive and the group will meet again in early September to review the drawings. |
Update on June 26, 2017 |
HGDI will commence topsoil stripping and earthworks construction for Phase 1 by the end of June as per the Topsoil Removal Permit. HGDI delivered Notices to residents as attached informing them on the works. A copy of the Construction Impact Mitigation Plan is posted for reference. |
Update on May 5, 2017 |
Update on April 18, 2017 |
Proposed Highland Gate Community Park |
Update on April 3, 2017 |
Update on March 16, 2017 |
HGDI will commence tree clearing works for Phase 1 on March 20, 2017 as per the Vegetation Management Agreement approved by the Town and in accordance with the Conditions of Subdivision approval. HGDI delivered Notices to residents on March 2, 2017 informing them of tree clearing works for Phase 1 was to commence in March 2017. See below notice posted on March 2, 201 |
Update on March 2, 2017 |
Update on February 22, 2017 |
Update on February 21, 2017 |
Update on December 1, 2016 |
Update on Highland Gate - Minutes of Settlement Released Minutes of Settlement regarding the redevelopment of the Highland Gate Golf Course were presented to the Ontario Municipal Board and verbally approved on Thursday, December 1, 2016. In addition, the proposed zoning by-law and Official Plan amendment, arising out of the Minutes of Settlement were also approved.
There will be no further hearing dates as the matter has now concluded |
Update for November 18, 2016 |
Update on Highland Gate Minutes of Settlement Signed by all Parties
A settlement hearing is scheduled for December 1, 2016 in the Council Chambers at Aurora Town Hall to present the settlement to the Ontario Municipal Board. A full copy of the Minutes of Settlement will be released following that hearing. |
Update November 2, 2016 |
Update on Highland Gate Settlement
Aurora, ON - On Wednesday, October 26, 2016, Aurora Town Council endorsed a settlement mediated by the Ontario Municipal Board on the appeal of the proposed redevelopment of the Highland Gate Golf Course, subject to the signing of Minutes of Settlement by all other parties.
|
Update October 26, 2016 |
Statement from The Town of Aurora
Aurora, ON – Aurora Town Council has endorsed a settlement mediated by the Ontario Municipal Board on the appeal of the proposed redevelopment of the Highland Gate golf course, subject to the execution of Minutes of Settlement by all other parties.
|
Update September 16, 2016 |
Ontario Municipal Board (OMB) update on Highland Gate
The Town of Aurora would like to provide residents with an update regarding the Ontario Municipal Board (OMB) case No. PL151160 regarding Highland Gate Developments Inc. at 21 Golf Links Drive.
|
Update July 14, 2016 |
The Ontario Municipal Board (OMB) has rescheduled the upcoming pre-hearing conference from August 22 and 23, 2016 to September 19, 2016.
|
Update May 25, 2016 |
On November 17, 2015, the Applicant led an appeal to the Ontario Municipal Board (OMB) on the proposed Planning Act applications for Highland Gate.
As directed by Council on December 8, 2015, the Town retained external legal counsel to represent the Town at the OMB regarding the appeal by Highland Gate Developments Inc.
An OMB pre-hearing is scheduled for Tuesday, March 22, 2016 at 10 a.m. in the Town Hall Council Chambers, Town of Aurora.
The pre-hearing will deal with preliminary and procedural matters including the following:
- Identification of parties
- Identification of participants
- Identification of issues
- Possibility of settlement of any or all of the issues
- Start date of the hearing
- Duration of the hearing
- The hearing of motions
- Such further matters as the Board considers appropriate
On December 8, 2015, Council adopted the following resolutions regarding the oer to sell by Highland Gate Developments Inc. and the related Ontario Municipal Board (OMB) appeal on this matter.
Please find the related Council extract from December 8, 2015 below.
Contact Us
Town of Aurora
100 John West Way
Aurora ON L4G 6J1
Phone: 905-727-1375 or 905-727-3123
Fax: 905-726-4769
Sign up to our Newsletter
Stay up to date on the city's activities, events, programs and operations by subscribing to our eNewsletters.